Capacity
Manufacturing → Capacity shows whether you have the hours for the work planned: each work centre by day or week, with the hours of work against the hours it has.
Read the grid
Section titled “Read the grid”Each cell shows the work and hours, such as 11/8h, with a percentage.
- Amber is from 80% full, and red is over 100%.
- No colour and no percentage means the work centre has no hours set, so there’s nothing to measure it against. Set its hours.
- A red cell on a day with no hours means there’s work on a day it doesn’t work.
- Late is work past its due date. It can’t be placed on a day, so it’s in its own column, and it’s usually the first thing to look at.
- All adds up every work centre, counting hours only for those that have them.
Select Days for the next two weeks, or Weeks for eight. Select a cell to see the operations behind it, with a link to each works order.
What’s counted
Section titled “What’s counted”Released and in-progress works orders, with the time left on each operation that isn’t done: its planned minutes less the time booked. Turn on Include drafts to see what’s coming too. Sale lines on To make with no works order yet aren’t counted, nor are works orders with no operations, and the screen says how many of those there are.
It’s an estimate
Section titled “It’s an estimate”Operations don’t have dates of their own, so Capacity works out when they’re likely to fall. Each works order’s operations take turns from its planned start, or today if that’s passed, to its due date, each with a share in proportion to its minutes. So a job with 1 hour of cutting and 4 of building, over five days, has its cutting on day 1 and an hour of building on each of the others.
This means:
- A day just over 100% may be fine, so look at the week as well.
- A works order with a long lead time looks like a little each day, even if it’s really done in two.
- The numbers are only as good as your routings.
Move work
Section titled “Move work”Capacity never moves a date by itself. If you can manage works orders, you can move work from the side panel, and the grid updates:
- Drag a works order onto a day, or a week, to start it then. With a mouse only.
- Or change its Start by or Due date in the panel, which also works on a phone.
Moving the start date spreads the work from there to its due date, so it won’t all land on the day you drop it on. To bring work together, move the due date as well.
If the new start is after its due date, you’re asked whether to move the due date too. That’s also how to deal with Late work: give it a new due date and it goes back on the grid. Press Esc while dragging to cancel.
These change the works order only. The date promised on an order doesn’t change, so check it if you move a due date past it.